    Yesterday, the service was affected due to capacity deficit from 06:12 to 01:49 in the morning (20:37 minutes).

    Unión Eléctrica pronostica una afectación de 515 MW en el horario pico nocturno

    The maximum impact at night was 880 MW at 6:40 p.m., coinciding with peak hour.

    The availability of the SEN at 07:00 hours is 1,860 MW and the demand is 1,975 MW, with 197 MW affected by capacity deficit in the SEN since 06:05 hours.

    It is estimated that service disruptions will occur during daylight hours, with a maximum impact of 550 MW.

    Units 6 and 7 of the CTE Mariel, unit 1 of the CTE Santa Cruz, unit 4 of the CTE Nuevitas, unit 2 of the CTE Felton and unit 3 of the CTE Renté are out of service due to a breakdown. Unit 8 of the Mariel CTE, unit 2 of the Santa Cruz CTE, the Guiteras CTE unit, unit 6 of the Nuevitas CTE and units 4 and 6 of the Renté CTE are under maintenance.

    The limitations on thermal generation (172 MW) are maintained.

    In distributed generation, 832 MW are unavailable due to failure and 421 MW are under maintenance.

    For peak hours, the entry of the CTE Guiteras unit with 220 MW (in the start-up process), the entry of the unit 3 of the CTE Rente with 65 MW (in the start-up process), the unit 2 of Energas Boca de Jaruco 30 MW, the completion of unit 6 of Energas Boca de Jaruco with 60 MW and the entry of 140 MW in diesel engines that arrived.

    With this forecast, an availability of 2,455 MW and a maximum demand of 2,900 MW are estimated for the peak hour, for a deficit of 445 MW, so if the forecast conditions are maintained, an impact of 515 MW is forecast during this time.