    The Directorate of the Electricity Company informs that during the weekend, interruptions were reported in the primary distribution lines of the Ciego Soya and Guayacanes circuits due to damaged devices.

    In addition, interruptions were reported in the secondary distribution lines (associated with transformers):

    • From the Gaspar circuit in the juvenile center, from the Morón Norte circuit on Estrella street between Marín and Simón Reyes, from La Ofelia circuit in Batey Viejo after La Ofelia and from the A110 circuit at El Ingenito farm due to damaged devices.
    • Circuit A110 in Tarea Confianza and circuit A 206 in the building in front of the Minaz due to animal contact with the network.
    • From the Nereida circuit in the Spanish block company due to contact of a tree with the network.

    For tomorrow, Tuesday, December 14, interruptions due to maintenance and pruning work are expected:

    • From the Colorado circuit at the Fidelito farm, El Hoyón, Las Coloradas, Dos Palmas, Quesada, Navarra, the Granado collection center and nearby places from 8:00 a.m. at 4:00 p.m.

    On affectations due to deficit in generation capacity:

     

     Yesterday and until the time of writing this informative note, there have been no effects due to a deficit in generation capacity and I do not know that they will occur in the morning and afternoon, if the expected conditions are maintained.

    Although various units of different thermoelectric plants are still out of service, due to breakdown and maintenance, an availability higher than demand is estimated for peak hours, so no effects on this schedule are forecast.

     We inform our clients of the schedule for today and tomorrow, in the event of unforeseen changes in the national electrical system.

    Impact plan for today, Monday, December 13, in the event of a generation capacity deficit:

    Block 3: From 8:00 a.m. at 12:00 m. in circuits 5, Cítrico II, Bolivia, La Cuba II, Micro Norte, Morón Centro, Combinado Minaz, Santana and Delfín Moreno.

    Block 4: From 12:00 m. at 4:00 p.m. circuits 1, A102, Cítrico I, Cítrico III, Cítrico IV, Ceballos, CAI Primero de Enero and Las Grullas.

    Block 5: From 4:00 to 8:00 p.m. on circuits A108, El Mambí, Vicente, Baraguá, Colorado, San Fernando, La Juanita, Violeta, Velazco, Montoto, Pablo, Tres Marías, Ognara, CAI Enrique Varona, Falla, Ranchuelo and Miraflores.

    Block 6: From 8:00 p.m. at 12:00 at night in the circuits in circuits A106, La Cuba II, Patria, Nereida, Polytechnic of Informatics, Peonia, Turiguanó, Chambas, Los Perros, El Asiento and Punta Alegre.

    Impact plan for tomorrow, Tuesday, December 14, in the event of a generation capacity deficit:

    Block 2: From 12:00 at night to 4:00 a.m. in circuits 2, La Piña, Jicotea, Guayacanes, Majagua, Orlando Gonzalez, Cuba Soy, Jagüeyal and Venezuela.

    Block 3: From 4:00 to 8:00 a.m. in circuits 5, Cítrico II, Bolivia, La Cuba II, Micro Norte, Morón Centro, Combinado Minaz, Santana and Delfín Moreno.

    Block 4: From 8:00 a.m. at 12:00 m. circuits 1, A102, Cítrico I, Cítrico III, Cítrico IV, Ceballos, CAI Primero de Enero and Las Grullas.

    Block 5: From 12:00 m. at 4:00 p.m. on circuits A108, El Mambí, Vicente, Baraguá, Colorado, San Fernando, La Juanita, Violeta, Velazco, Montoto, Pablo, Tres Marías, Ognara, CAI Enrique Varona, Falla, Ranchuelo and Miraflores.

    Block 6: From 4:00 to 8:00 p.m. in circuits A106, La Cuba II, Patria, Nereida, Polytechnic of Informatics, Peonia, Turiguanó, Chambas, Los Perros, El Asiento and Punta Alegre. Block 1: From 8:00 p.m. at 12:00 at night in circuits 3, A104, A206, La Cuba, Morón Sur, Florencia and Tamarindo.

    THE ELECTRICITY COMPANY OFFERS APOLOGIES FOR THE ANNOYANCE.