    The Electric Power Company reported that for this day, an availability of 2,513 MW and a maximum demand of 2,900 MW are estimated for peak hours, for a deficit of 387 MW, so if the expected conditions are maintained, an affectation of 450 is forecast. MW at peak.

    Regarding to the note, this Tuesday the service was affected by capacity deficit 24 hours a day. The maximum affectation during peak hours was 611 MW at 8:40 p.m. Unit 1 of the CTE Lidio Ramón Perez joined the SEN at 02:28 am today.

    Service was restored at 4:04 a.m. today. It is forecast that the service will begin to be affected by a generation capacity deficit at 08:00 hours, with a maximum of 400 MW at noon.

    According to the UNE, units 6 and 7 of the CTE Máximo Gómez and unit 5 of the CTE Antonio Maceo are out of service due to breakdowns. CTE unit Otto Parellada, CTE unit 2 Lidio Ramón Pérez and CTE unit 6 Antonio Maceo are under maintenance.

    The limitations in thermal generation (579 MW) are maintained. In distributed generation, 1,071 MW are unavailable due to breakdown and 410 MW are undergoing maintenance. For peak hours, the use of 117 MW in diesel engines.