    Yesterday, the service was affected by capacity deficit throughout the day. The maximum affectation at night was 515 MW at 8:40 p.m. Service was restored at 12:45 a.m. today.

    Información de la Unión Eléctrica

    Starting at 08:00 hours, the service will begin to be affected throughout the day today, with a maximum of 350 MW during daytime hours.

    Units 6, 7 and 8 of CTE Máximo Gómez, CTE Otto Parellada unit, CTE unit 2 Lidio Ramón Pérez and CTE unit 3 Antonio Maceo are out of service due to breakdowns.

    Unit 5 of the CTE Máximo Gómez is under maintenance. Limitations on thermal generation (555 MW) are maintained.

    In distributed generation, 1,035 MW are unavailable due to breakdown and 395 MW are undergoing maintenance.

    For peak hours, the entry of the Otto Parellada CTE unit with 40 MW (in the startup process), the entry of the Ciro Redondo Bioelectric Plant with 20 MW and the use of 124 MW in diesel engines is forecast.

    With this forecast, an availability of 2,657 MW and a maximum demand of 2,900 MW are estimated for peak hours, for a deficit of 243 MW, so if the forecast conditions are maintained, an affectation of 313 MW is forecast at the peak, It is estimated that the service will be restored at 01:00 am tomorrow morning.

    All consumption restriction measures are implemented in the state sector.