    Pequeña  mejoría en afectación eléctrica este jueves

    This Wednesday, the service was affected by generation capacity deficit throughout the day. The maximum impact at night was 1,414 MW at 8:00 p.m., coinciding with peak hour, including 111 MW due to damage caused by Hurricane Ian.

    The Electric Union informs that for the daytime hours of this Thursday a maximum affectation of 850 MW is estimated due to a deficit in generation capacity.

    CTE Mariel units 6 and 7, CTE Otto Parellada unit, CTE Nuevitas units 4 and 6, CTE Felton unit 2 and CTE units 4 and 6 are out of service due to breakdowns. Rent. Under maintenance is unit 3 of the CTE Rente.

    The limitations in thermal generation (637 MW) are maintained.

    In distributed generation, 1,072 MW are not available due to breakdown, and in maintenance, 690 MW.

    For the peak hours of this day, the entry of 130 MW in diesel engines is expected.

    With this forecast, the UNE estimates for the peak hour of this Thursday an availability of 2,252 MW and a maximum demand of 3,150 MW, for a deficit of 898 MW, so that, if the forecast conditions are maintained, an affectation is forecast of 968 MW at that time, 105 MW as a result of the damage caused by Ian.