    0821 felton

    The Electric Power Company reports that yesterday the electrical service was affected from 5:18 p.m. to 7:28 p.m. The maximum impact was 326 MW at 6:20 p.m.

    The availability of the SEN at 07:00 hours is 2,150 MW and the demand is 1,900 MW, without affecting the service due to capacity deficit in the SEN. It is estimated that during the daytime the service will not be affected due to capacity deficit in the SEN.

    Units 6 and 7 of the CTE Mariel, unit 4 of the CTE Nuevitas, unit 4 of the CTE Rente and unit 2 of the CTE Felton are out of service due to a breakdown. Unit 1 of the CTE Santa Cruz and unit 3 of the CTE Renté are under maintenance.

    The limitations on thermal generation (352 MW) are maintained. In distributed generation, 888 MW are unavailable due to failure and 598 MW are under maintenance.

    For peak hours, the completion of unit 1 of the CTE Felton with 140 MW and the entry of 247 MW in diesel engines are estimated.

    With this forecast, an availability of 2,567 MW and a maximum demand of 2,750 MW are estimated for the peak hour, for a deficit of 183 MW, so if the forecast conditions are maintained, an impact of 253 MW is forecast during this time.