    The Electric Power Company forecasts an affectation of 58 MW for the night peak hours

    Star InactiveStar InactiveStar InactiveStar InactiveStar Inactive
     
    Rating:
    ( 0 Rating )
    Pin It

    La Unión Eléctrica pronostica una afectación de 58 MW para el horario pico nocturno

    The Electric Power Company estimates that for the night peak hours of this Tuesday there will be an availability of 2,732 MW and a maximum demand of 2,720 MW, for a reserve of 12 MW. If the predicted conditions are maintained, an affectation to the service of 58 MW is forecast at that time.

    The availability of the SEN at 07:00 hours was 2,160 MW and the demand was 1,920 MW, with the entire system with service. It is estimated that during the daytime the service will not be affected, the entity reported.

    Yesterday, it was possible to cover the demand throughout the day.

    Units 6 and 7 of the CTE Mariel, unit 1 of the CTE Santa Cruz, units 4, 5 and 6 of the CTE Nuevitas, unit 2 of the CTE Felton and unit 5 of the CTE I rented. Unit 5 of the CTE Mariel, unit 2 of the CTE Santa Cruz and units 4 and 6 of the CTE Renté are under maintenance.

    Limitations persist in thermal generation (332 MW). Meanwhile, in distributed generation, 821 MW are unavailable due to failure and 474 MW are under maintenance.

    For peak hours, the completion of unit 6 of Energas Boca de Jaruco with 40 MW, the entry of unit 1 of CTE Santa Cruz with 80 MW, the entry of Patana de Melones with 75 MW, the completion of unit 3 of the CTE Cienfuegos with 85 MW and the entry of 292 MW in diesel engines.