    Yesterday, the service was affected due to a generation capacity deficit from 06:15 to 07:07 (52 minutes) with a maximum impact of 70 MW and from 08:44 to 02:23 hours of the early morning today (17 hours and 39 minutes).

    The maximum impact at night was 820 MW, at 8:30 p.m., coinciding with peak time.

    The availability of the SEN at 07:00 hours is 2,010 MW and the demand is 2,000 MW, with the entire system with service. It is estimated that there will be disruptions to the service due to a deficit in generation capacity starting at 08:00 a.m. with a maximum of 350 MW.

    Unit 8 of the CTE Mariel, unit 3 of the CTE Cienfuegos and unit 2 of the CTE Felton are out of service due to a breakdown. Unit 5 of the CTE Mariel, unit 3 of the CTE Santa Cruz, unit of the CTE Guiteras, unit 4 of the CTE Cienfuegos, unit 6 of the CTE Diez de Octubre and units 4 and 6 of the CTE Renté.

    Limitations on thermal generation (259 MW) are maintained. In distributed generation, 909 MW are unavailable due to failure and 119 MW are under maintenance.

    For the peak, the entry of the Puerto Escondido unit with 20 MW and the recovery of 146 MW of generation engines are expected.

    With this forecast, an availability of 2,176 MW and a maximum demand of 2,820 MW are estimated for the peak hour, for a deficit of 644 MW, so that if the forecast conditions are maintained, an affectation of 714 MW is forecast during this time.